Explanatory video about the rules for external construction work [Part 1] (English)

Information

This video explains the rules that must be observed when performing external construction work on the premises of Toyota Boshoku Corporation.

Please use this during morning meetings and toolbox meetings.

*Each link will open in a new tab.

Construction Manager

All Segmented Version
01 Qualification certificate etc.
02 Business cycle
03 Main mission

Person in charge of work

All Segmented Version
01 Qualification certificate etc.
02 Business cycle
03 Main mission

Mixed work

All Segmented Version

01 What is mixed work
02 About the plan
03 Appoint a general manager

Electrical work

All Segmented Version
01 Protective equipment
02 Power Disconnect and Lockout
03 Electricity check confirmation
04 Power tools
05 6-month inspection of power tools

Chemical substance handling work

All Segmented Version
01 Fire
02 Chemicals
03 Water pollution
04 Ventilation
05 Protective equipment

Hot work : General

All Segmented Version
01 Fire extinguishing equipment/banner
02 Combustible material confirmation
03 Check for embers

Hot work : Grinder

All Segmented Version
01 Pre-work inspection
02 Protective equipment
03 Fireproof sheet
04 Storage of grinding stones, etc.

Hot work : Arc welding/cutting

All Segmented Version
01 Arc welding pre-start inspection
02 Arc welding ground installation
03 Arc welding cable protection
04 Arc welding protective equipment
05 Arc welding management method
06 Gas welding pre-start inspection
07 Gas welding protective equipment
08 Gas welding working at height
09 Gas welding management method

Dangerous work involving oxygen deficiency, hydrogen sulfide, and gas vapor

All Segmented Version
01 Emergency confirmation
02 Workplace Environment
03 Protective equipment
04 Confirmation of personnel

Work at height : General

All Segmented Version
01 Safety education qualification
02 Safety equipment
03 Measures to be taken when a work platform cannot be installed
04 Fall prevention measures
05 Lifting equipment
06 Banner
07 Measures to be taken in bad weather

Work at height : Scaffolding

All Segmented Version
01 Work platform specification
02 Measures to prevent flying objects and falling objects
03 Leading handrail etc.
04 Precautions when making installment payments
05 Near overhead power lines
06 Scaffolding inspection

Work at height : Working on the roof

All Segmented Version
01 Slate roof safety equipment
02 Measures for dangerous areas
03 How to place materials
04 Measures around windows
05 Others

Work at height : Ladder

All Segmented Version
01 Ladder specifications
02 Installation method
03 Measures to prevent falls
04 When going up and down

Work at height : Stepladder

All Segmented Version
01 Ladder specifications
02 Precautions for using stepladders